A solar farm and battery off Bewlbridge Lane would supply about 38% of the power used at South East Water's Bewl works. Comments close on 8 December.
A solar farm with battery storage is planned for a field beside Bewl Water, near Lamberhurst, to power South East Water’s treatment works next door. It would supply about 38% of the electricity the works uses and keep it running if the mains supply fails. Comments to Tunbridge Wells Borough Council close on Tuesday 8 December.
The site is on land east of Bewlbridge Lane, about a kilometre south of Lamberhurst village and about seven miles south-east of Royal Tunbridge Wells. The council validated the application, 26/02515/FULL, on Tuesday 17 November. The applicant is Ennoviga Solar Ltd.
Power for the works, not the grid
Most solar farms sell their power into the National Grid. This one would not. The planning statement says it would be wired “behind the meter” into the private network of the Bewl Water Treatment Works, about 200m to the south-west.
The whole output of the panels and the battery is contracted to South East Water for use at the works. The statement gives these figures:
- about 4 GWh of electricity in a typical year
- about 38% of the electricity the works consumes
- about 525 tonnes of carbon dioxide equivalent saved each year
The battery is there for resilience as well as cost. If the incoming electricity supply is interrupted, the statement says, the battery would be used “to keep the Water Works operating”.
South East Water sent its own statement with the application. It says it is upgrading the treatment capacity of the Bewl works, and that the power supply has been designed to serve the upgraded works. It also says solar at the works costs less than buying renewable power on the market, and helps it towards the water industry’s target of net zero operations by 2030.
What would be built
The planning statement and the drawings describe:
- rows of panels on metal frames driven into the ground, no taller than 3.5m, facing south
- a fenced area of about 4.4 hectares inside a 5.3 hectare field
- two battery containers, each up to 6.8m long and 2.8m wide, in the north-west corner
- CCTV cameras on poles up to 5m high around the fence
- no permanent lighting
- an underground cable to the works alongside Bewlbridge Lane
Permission is sought for 40 years. After that the equipment would be removed and the field returned to farming, which the statement says is secured by condition and by the lease.
The High Weald question
The whole site is inside the High Weald National Landscape, formerly the Area of Outstanding Natural Beauty. National policy sets a high bar for “major development” in such areas.
The applicant argues the scheme is not major development, given its size and setting. If the council disagrees, it argues there are exceptional circumstances: the panels must sit close to the works to be wired straight in, and the works is itself inside the National Landscape. The statement notes that 68.88% of the borough lies within the designation.
It accepts some harm. The scheme would take about 1.65 hectares of “best and most versatile” farmland out of use for its lifetime. The soil survey found about a third of the developed area was Grade 3a, good quality land, and the rest Grade 3b, moderate quality land limited by wetness.
The statement also says:
- there is no public footpath across or beside the site
- the nearest listed buildings are Little Bewl Bridge Farmhouse, about 400m to the north-east, and Hillside Cottage, about 500m to the north-east, both Grade II
- Lamberhurst’s conservation area is about 1km to the north
- the ecology work shows a 148.44% biodiversity net gain on the site, against a legal minimum of 10%
The applicant shared the plans with the High Weald National Landscape Unit and the Friends of Bewl Water before submitting them. When the statement was written, it was still waiting for the Friends of Bewl Water to respond. The High Weald unit said it would comment through the planning process.
Construction traffic on Bewlbridge Lane
Building it would take about 8 to 12 weeks. The transport statement estimates 37 to 48 lorry deliveries in total, or 74 to 96 lorry movements counting arrivals and departures separately. On top of that would be two to four trips a day by contractors’ cars and vans.
Lorries would use the existing farm gate on Bewlbridge Lane. Once running, the site would need a car or van one or two times a month for maintenance.
What the Environment Agency said
The Environment Agency replied on 17 November with no objection. It did ask the council to make sure there is a plan for a battery fire. Water used to cool batteries, or rain falling on burnt containers, could carry “highly polluting chemicals” into groundwater, it said, so that water needs to be contained and taken off site.
The planning statement says the applicant met Kent and East Sussex fire services about the batteries on 8 October.
What it means for you
- If you live near Bewlbridge Lane or use it to reach Bewl Water, expect lorries for two to three months if the scheme is approved and built. The applicant expects a construction traffic plan to be required by condition.
- If you want a say, comment on the application’s page on the council’s planning portal by 8 December. The council’s register says the application is also due to be advertised in the press on 27 November, with that notice running to 18 December.
- The decision is expected to be made by council officers rather than the planning committee, according to the register. It is due by 16 February 2027.
Also on this week’s planning list
Two more solar schemes were on the council’s weekly list for the week starting 16 November, both on roofs:
- Tunbridge Wells Boys’ Grammar School, St John’s Road. Prior notification for solar panels on the roof (26/02529/PN14J).
- Kingswood Surgery, Kingswood Road. Solar panels on the roof (26/02468/FULL).
Have your say